Excel-driven benchmark

1 MW / 2 MWh BESS BoQ and price benchmark.

This page is generated directly from the workbook in the project folder. It is a screening-level benchmark, not a commercial offer. When you are ready to buy, we move into a managed procurement offer process.

FieldMarketOffer

Packages

11

BoQ items

72

Sources

10

Pricing use

Screening only

Best next step

Case study review

Commercial use

Supplier offer required

Cost packages

Procurement packages from the Excel workbook.

Use these as screening-level benchmarks only. They are intentionally conservative for a small project and should be replaced by supplier-backed procurement offers before commercial use.

Benchmark use only, not live supplier pricing.

These values are indicative planning references, not a binding offer or guaranteed market price. Small-volume unit pricing can be conservative, and final pricing may change materially with volume, framework purchasing, supplier allocation, logistics, Incoterms, warranty scope and documentation requirements.

IDPackageScopeQtyLowBaseHighConfidence
P01Integrated battery container / cabinetsBattery cells/modules/racks, BMS, enclosure/container, thermal management, fire detection/suppression as OEM-integrated scope2 MWh€200,000€330,000€500,000Medium
P02PCS / bidirectional inverter package1 MW PCS including enclosure/skid, controls, DC/AC protection interface, cooling and basic filters1 MW€40,000€70,000€120,000Medium-Low
P03LV/MV transformerApprox. 1.25 MVA step-up transformer, pad, oil containment if applicable1.25 MVA€20,000€35,000€60,000Low-Medium
P04MV switchgear, protection and revenue meteringMV switchgear/RMU, relays, CT/VT, meters, surge arresters and grid-interface cabinets1 lot€20,000€40,000€80,000Low-Medium
P05EMS / SCADA / PPC / RTU / communicationsEMS, plant controller, SCADA, HMI, RTU/gateway, network, cybersecurity and remote monitoring interface1 lot€20,000€45,000€90,000Medium
P06EBOS, auxiliary power, cabling, groundingLV/DC/MV cabling inside site, trays/ducts, earthing grid, lightning protection, auxiliary transformer/panel, UPS1 lot€25,000€50,000€100,000Medium-Low
P07Civil, site preparation, fencing and securitySurveys, grading, pads/foundations, access road/hardstanding, drainage, fence/gate, CCTV/lighting1 lot€25,000€50,000€100,000Medium-Low
P08Installation, FAT/SAT and commissioningOn-site structural/electrical labor, unloading, installation, tests, energization, commissioning and reliability run1 lot€30,000€70,000€130,000Medium-Low
P09Engineering, permitting and interconnection studiesElectrical/civil design, studies, permitting documentation, protection settings, environmental/admin support1 lot€20,000€40,000€80,000Medium-Low
P10Spares, warranty uplift and contingencyInitial spares, consumables, warranty/reserve allowances and contingency1 lot€35,000€70,000€120,000Medium-Low
TOTALNon-overlapping CAPEX subtotal €435,000€800,000€1,380,000

BoQ benchmarks

Line-item view grouped by technical section.

The BoQ rows are parsed from the `BoQ_Benchmarks` worksheet and grouped for easier procurement review.

Benchmark use only, not live supplier pricing.

These values are indicative planning references, not a binding offer or guaranteed market price. Small-volume unit pricing can be conservative, and final pricing may change materially with volume, framework purchasing, supplier allocation, logistics, Incoterms, warranty scope and documentation requirements.

Battery block

ItemComponentBasisBase EURRange EURConfidence
B01LFP battery cells2,000–2,300 nominal kWh equivalent€190,000€120,000 - €280,000Medium
B02Battery modulesOEM-integrated€45,000€20,000 - €80,000Low
B03Battery racks / cabinets6–10 racks or OEM-equivalent€60,000€25,000 - €110,000Low-Medium
B04Battery container / outdoor enclosure1 x 20 ft / cabinet set€60,000€25,000 - €120,000Low

Battery control

ItemComponentBasisBase EURRange EURConfidence
B05Master BMS1€20,000€8,000 - €45,000Low
B06Rack / string BMS1 per rack/string€15,000€5,000 - €30,000Low
B07Cell monitoring units / sensorsOEM-integrated€8,000€3,000 - €18,000Low

DC protection

ItemComponentBasisBase EURRange EURConfidence
B08DC contactorsPer rack/string€8,000€3,000 - €18,000Low
B09DC fusesPer rack/string€6,000€2,000 - €14,000Low
B10DC disconnect switches1 set€8,000€3,000 - €18,000Low
B11DC combiner panel1–2€12,000€5,000 - €30,000Low-Medium

DC balance

ItemComponentBasisBase EURRange EURConfidence
B12DC cabling and terminations1 lot€15,000€6,000 - €35,000Low

DC safety

ItemComponentBasisBase EURRange EURConfidence
B13DC insulation monitoring1€6,000€2,000 - €15,000Low

Safety

ItemComponentBasisBase EURRange EURConfidence
B14Emergency stop circuit and buttons2–4 stations€6,000€2,000 - €12,000Low

Thermal management

ItemComponentBasisBase EURRange EURConfidence
T01HVAC units / container cooling1–2€35,000€15,000 - €70,000Low-Medium
T02Liquid cooling loop / manifoldsIf liquid-cooled€25,000€10,000 - €60,000Low
T03Coolant / glycol and leak detection1€6,000€2,000 - €15,000Low
T04Normal and emergency ventilation1€15,000€5,000 - €35,000Low

Fire safety

ItemComponentBasisBase EURRange EURConfidence
F01Fire detection panel1€8,000€3,000 - €18,000Low-Medium
F02Smoke / heat detectors1 lot€4,000€1,500 - €10,000Low
F03Gas detectors1 lot€8,000€3,000 - €18,000Low
F04Aerosol / clean agent / water mist suppression1€25,000€8,000 - €60,000Low-Medium
F05Explosion relief / deflagration ventingIf required€15,000€5,000 - €40,000Low
F06Fire extinguishers, signage, emergency response pack1 lot€3,000€1,000 - €8,000Low

Power conversion

ItemComponentBasisBase EURRange EURConfidence
PWR01PCS / bidirectional inverter1 MW€70,000€40,000 - €120,000Medium
PWR02PCS enclosure / skid1€12,000€5,000 - €25,000Low
PWR03PCS controller1€10,000€3,000 - €25,000Low
PWR04AC/DC breakers, harmonic filters, PCS cooling1€20,000€8,000 - €45,000Low

Transformer

ItemComponentBasisBase EURRange EURConfidence
TR01LV/MV step-up transformer 1.25 MVA1€35,000€20,000 - €60,000Low-Medium
TR02Transformer foundation / oil bund1€12,000€5,000 - €25,000Low

MV interface

ItemComponentBasisBase EURRange EURConfidence
MV01MV switchgear / RMU 20 kV class1€30,000€15,000 - €60,000Low
MV06MV cable, terminations and jointsSite length dependent€25,000€8,000 - €70,000Low

MV protection

ItemComponentBasisBase EURRange EURConfidence
MV02Protection relay + settings hardware1€12,000€5,000 - €30,000Low
MV03CTs / VTs1€10,000€4,000 - €25,000Low
MV07Surge arresters and earthing switches1€8,000€3,000 - €18,000Low

Metering

ItemComponentBasisBase EURRange EURConfidence
MV04Revenue metering cabinet1€12,000€5,000 - €25,000Low
MV05Check meterOptional€6,000€2,000 - €12,000Low

Auxiliary power

ItemComponentBasisBase EURRange EURConfidence
AUX01Auxiliary transformer25–50 kVA if needed€8,000€3,000 - €18,000Low
AUX02LV auxiliary power panel1€10,000€4,000 - €25,000Low
AUX03UPS for controls/protection1€8,000€3,000 - €20,000Low

Control & software

ItemComponentBasisBase EURRange EURConfidence
CTRL01EMS1€35,000€15,000 - €80,000Medium-Low
CTRL02Plant controller / PPC1€20,000€8,000 - €50,000Low-Medium
CTRL03SCADA + HMI workstation1€20,000€8,000 - €50,000Low-Medium

Communications

ItemComponentBasisBase EURRange EURConfidence
CTRL04RTU / gateway1€15,000€5,000 - €35,000Low-Medium
CTRL05Network switches / fiber / firewall1€15,000€5,000 - €35,000Low
CTRL06GPS / NTP time synchronization1€6,000€2,000 - €15,000Low

Data

ItemComponentBasisBase EURRange EURConfidence
CTRL07Data historian / remote monitoring1€15,000€5,000 - €40,000Low

Market interface

ItemComponentBasisBase EURRange EURConfidence
CTRL08Commercial optimizer / route-to-market interfaceOptional€25,000€0 - €100,000Low

Electrical BoP

ItemComponentBasisBase EURRange EURConfidence
EBOS01LV AC cablingSite length dependent€15,000€5,000 - €40,000Low
EBOS02Cable trays / ladders1€10,000€3,000 - €25,000Low
EBOS03Underground ducts / pull boxes1€15,000€5,000 - €40,000Low
EBOS04Earthing grid / rods / tape1€15,000€5,000 - €35,000Low-Medium
EBOS05Lightning protection1€8,000€3,000 - €20,000Low

Engineering studies

ItemComponentBasisBase EURRange EURConfidence
EBOS06Short-circuit, load flow, protection coordination, harmonic/power quality1€20,000€8,000 - €50,000Low-Medium

Civil/site

ItemComponentBasisBase EURRange EURConfidence
CIV01Topographic survey1€3,000€1,000 - €8,000Low
CIV02Geotechnical study1€6,000€2,000 - €15,000Low
CIV03Site clearing, grading, compaction, drainage1€25,000€10,000 - €60,000Low-Medium
CIV04BESS/PCS/MV foundations and concrete pads1€35,000€15,000 - €80,000Low-Medium
CIV05Access road / hardstanding / crane pad1€25,000€10,000 - €60,000Low-Medium
CIV06Security fence and gate1€15,000€5,000 - €40,000Low-Medium
CIV07Outdoor lighting1€8,000€3,000 - €20,000Low

Security

ItemComponentBasisBase EURRange EURConfidence
SEC01CCTV / intrusion detection / access control1€15,000€5,000 - €40,000Low-Medium

Site safety

ItemComponentBasisBase EURRange EURConfidence
SAFE01PPE, rescue equipment and safety signage1€4,000€1,000 - €10,000Low
SAFE02Arc-flash study and labels1€8,000€3,000 - €20,000Low

Documentation

ItemComponentBasisBase EURRange EURConfidence
DOC01Design drawings and as-built documentation1€20,000€8,000 - €50,000Low-Medium

Testing

ItemComponentBasisBase EURRange EURConfidence
DOC02FAT procedure and witness testing1€15,000€5,000 - €40,000Low
DOC03SAT, commissioning, capacity/power/RTE tests1€35,000€15,000 - €90,000Low-Medium

Spares

ItemComponentBasisBase EURRange EURConfidence
SP01DC fuses / relays / filters / detector spares1€15,000€5,000 - €40,000Low
SP02Optional spare battery module / PCS boardOptional€35,000€10,000 - €90,000Low

Excluded / optional

ItemComponentBasisBase EURRange EURConfidence
OPEX01Long-term O&M / LTSAAnnual€35,000€15,000 - €80,000Low

Excluded / site-specific

ItemComponentBasisBase EURRange EURConfidence
GRID01External grid reinforcement / connection line beyond compoundSite-specific€0€0 - €0High
DEV01Land rights, legal DD, development premium, ANRE fees, financing costsSite-specific€0€0 - €0High

Methodology

Workbook assumptions and source basis.

Benchmark context

This benchmark is a screening tool for a 1 MW / 2 MWh BESS package. It is not a quote, not a binding offer and not a guarantee of supplier allocation.

Project definition

Standalone BESS, front-of-meter, 1 MW AC / 2 MWh usable, approx. 2-hour duration, LFP technology.

Currency

EUR primary; USD columns derived using Dashboard EUR/USD assumption.

Benchmark nature

Order-of-magnitude May 2026 screening benchmark only; not a supplier quotation and not a fixed price.

Scope boundary

Includes BESS compound equipment and normal EPC items up to MV/grid-interface point; excludes external grid reinforcement unless separately noted.

Main high-quality public benchmark

NREL 2025 update for utility-scale battery storage; 2026 4-hour complete-system benchmark and component taxonomy.

Market floor

Reuters/Ember and BNEF indicate much lower China/global pack/core equipment pricing; small 1 MW / 2 MWh projects in Europe may not capture those large-project economics.

How ranges were set

Triangulation: (i) NREL cost model, (ii) BNEF pack prices, (iii) IRENA global BESS cost, (iv) Reuters/Ember market floor, (v) component-specific professional estimates.

Double-counting warning

Use Cost_Packages for non-overlapping roll-up. Use BoQ_Benchmarks for component understanding; many child components are included in parent packages.

Bankability adjustment

The base case assumes bankable equipment and warranty terms; suspiciously low supplier prices were not used as the primary base.

VAT / taxes

VAT and import duties are not specifically modelled; US NREL values include US-style sales tax categories but the EUR package values are adjusted for practical screening.

Romanian grid costs

Connection tariff, ATR-specific works, grid reinforcements and ANRE costs are excluded and must be separately assessed.

Sources

Public benchmark references captured in the workbook.

NREL | High

Cost Projections for Utility-Scale Battery Storage: 2025 Update

2026 4h complete system: $255/$308/$366 per kWh low/mid/high; component taxonomy includes cabinets, inverter, SBOS, EBOS, labor, permitting, contingency, overhead and profit. 2024 energy/power split: $241/kWh energy + $372/kW power.

PNNL | High

Energy Storage Cost and Performance Database

Interactive total installed cost ranges by technology, year, MW and duration; covers LFP/NMC and other storage technologies.

BloombergNEF | High

2025 Lithium-Ion Battery Price Survey press release

Stationary storage battery packs fell to $70/kWh in 2025; average LFP packs $81/kWh; China average $84/kWh, North America +44%, Europe +56%.

Reuters / Ember | Medium-High

Reuters Events article citing Ember battery project costs

Average global battery project costs $125/kWh in Dec 2025: $75/kWh core equipment from China + $50/kWh installation and connection.

IRENA | High

Renewable Power Generation Costs in 2024

Utility-scale BESS installed costs fell to $192/kWh in 2024, 93% below 2010.

DOE | High

Battery Energy Storage Systems Report / BESSIE supply chain report

Describes BESS components and site control/EMS architecture, communications and safety systems.

xBrele | Low-Medium

Distribution transformer manufacturers and cost ranges

Public 1000 kVA transformer example: tier-1 $15k–$25k, lower-tier $8k–$12k.

Schneider Electric | Medium

Medium voltage switchgear product category

MV switchgear types: AIS/GIS/solid-insulated; SF6-free option. No direct pricing.

ABB | Medium

Medium voltage switchgear product category

MV switchgear scope for grid connection/protection; no direct pricing.

FX | Medium

EUR/USD historical daily data

EUR/USD around 1.164 on 26 May 2026; used for USD conversion.

FAQ

BESS benchmark questions.

Is the BESS benchmark live supplier pricing?

No. It is indicative planning data generated from the workbook and public benchmark inputs. Commercial use requires supplier-backed procurement offers.

Why can small-package unit prices look high?

Small-volume procurement can carry conservative unit pricing. Larger volumes, framework purchasing, supplier allocation and optimized logistics can materially reduce final unit cost.

What should a buyer do after reviewing the benchmark?

The buyer should send the BoQ or technical requirement so Joultra can qualify the scope and request supplier-backed procurement input through a protected process.